M/S Fabtech Projects And Engineers Ltd v. Indian Oil Corporation Limited
$~92 * IN THE HIGH COURT OF DELHI AT NEW DELHI + ARB.P. 1736/2025 M/S FABTECH PROJECTS AND ENGINEERS LTD .....Petitioner Through:
Mr. Vaibhav Gaggar, Sr. Adv. with Mr. Saurabh Mishra, Adv.
versus INDIAN OIL CORPORATION LIMITED .....Respondent Through:
CORAM:
HON'BLE MR. JUSTICE JASMEET SINGH
O R D E R
% 17.10.2025 1.
This is a petition filed under Section 11 of the Arbitration and Conciliation Act, 1996 ("Act") seeking appointment of an arbitrator arising out of a Fax of Acceptance awarding the work to the petitioner on lump sum turn key basis for LPG storage & dispatch facilities and offsite & utilities at Bongaigaon Refinery, Assam, Indiadated 23.02.2017. 2.
A perusal of the paper book shows that no notice under Section 21 of the Act has been issued.
3.
Mr. Gaggar, learned senior counsel for the petitioner, on instructions, seeks to withdraw the petition and file a fresh petition after serving the notice under Section 21 of the Act.
4.
Granting the said liberty, the petition is disposed of. JASMEET SINGH, J OCTOBER 17, 2025/AS The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 25/10/2025 at 13:59:51