IN THE HIGH COURT OF DELHI AT NEW DELHI

+ W.P.(C) 17759/2025 MOHD ARIF .....Petitioner Through:

Mr. Nikhil Tuteja with Mr. Atul Bhojane, Advocates (through VC).

versus MUNICIPAL CORPORATION OF DELHI THROUGH ITS COMMISIONER & ORS.

.....Respondents Through:

Ms. Ankita Trivedi, Advocate for R-2 & 3 (through VC).

Mr.

Ashok Kumar Choudhary, Advocate for R-2 & 3.

Mr. S. Tabrez with Mr. Saifi Ahmad, Advocates for R-4.

Ms. Vidhi Jain with Ms. Namisha Chadha, Advocates for MCD.

CORAM:

HON'BLE MR. JUSTICE AMIT BANSAL

O R D E R

% 22.05.2026 1.

The present writ petition has been filed seeking a direction to the respondents no.1, 2 and 3 to take appropriate action for removal/demolition of unauthorised construction carried out by the respondent no. 4 up to the 8th floor at Khasra No. 27/327/8/1, Street No.10, Sangam Vihar, Jharoda Majra, Burari, North Delhi - 110084 (hereinafter 'subject property') and subsequently seal the same.

2.

Status report has been filed on behalf of the respondent no.1/MCD, wherein it is stated that a demolition order against the subject property has been passed on 2nd January, 2026. The demolition action was fixed on 17th W.P.(C) 17759/2025 The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 25/05/2026 at 13:12:28

February, 2026, but could not be carried out on the said date due to the nonavailability of Police force. Subsequently, the same was fixed for 13th May, 2026.

3.

Counsel appearing for the respondent no.1/MCD submits that the demolition action was taken on 13th May, 2026 and portion on the sixth floor of the subject property has been demolished.

4.

Counsel for the petitioner is satisfied with the aforesaid action taken by MCD.

5.

Accordingly, the present writ petition is disposed of as satisfied. AMIT BANSAL, J MAY 22, 2026 Rzu W.P.(C) 17759/2025 The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 25/05/2026 at 13:12:28