IN THE HIGH COURT OF DELHI AT NEW DELHI
+ ARB.P. 299/2016 XJ ELEVATORS INDIA PVT LTD ..... Petitioner Through Mr. Salar M. Khan and Mr. Kaushelendra Singh, Advocates versus NOVELL CONSTRUCTIONS ..... Respondent Through None
CORAM:
HON'BLE MR. JUSTICE MANMOHAN SINGH
O R D E R
% 01.06.2016 The respondent has paid the settled amount of Rs.92,500/- to the learned counsel for the petitioner. The cheque was issued in the name of the petitioner.
Learned counsel for the petitioner submits that subject to the encashment of the cheque issued by the respondent, the present petition be treated as closed.
The same is accordingly disposed of.
MANMOHAN SINGH, J.