Sh Virender Singh Khatri v. Govt Of NCT Of Delhi I And Fc Department
$~18 *
IN THE HIGH COURT OF DELHI AT NEW DELHI
+ ARB.P. 2021/2025 SH VIRENDER SINGH KHATRI .....Petitioner Through:
Mr. Avinash Trivedi and Mr Rahul Aggarwal, Advs.
versus GOVT OF NCT OF DELHI I AND FC DEPARTMENT .....Respondent Through:
Mr Abhinav Sharma, Mr Shubham Advs.
CORAM:
HON'BLE MR. JUSTICE JASMEET SINGH
O R D E R
% 23.12.2025 1.
This is a petition filed under Section 11(6) of the Arbitration and Conciliation Act, 1996 seeking appointment of an Arbitrator for adjudication of disputes between the parties. 2.
The brief facts are that the respondent awarded the petitioner the work of "Construction of Roads/Galies and culvert in D & E Block in J.J. Colony in Bawana Assembly Constituency" vide Letter of Acceptance dated 21.04.2016. Thereafter, the respondent issued the Letter of Commencement of work dated 06.05.2016. Pursuant to which the parties entered into an Agreement dated 06.05.2016. 3.
Later, the respondent awarded the work of " Improvement of road from Lal Ghar to Police Booth road in J.J. Colony in Bawana Assembly Constituency " vide Letter of Acceptance dated 09.05.2016. Thereafter, the respondent had issued the Letter of Commencement of work dated 20.05.2016. Pursuant to which the parties entered into an Agreement dated 09.05.2016.
4.
The said Agreement contains an arbitration clause being Clause No. The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above.
25 of the GCC, which reads as under:- "CLAUSE 25 Settlement of Disputes & Arbitration Except where otherwise provided in the contract, all questions and disputes relating to the meaning of the specifications, design, drawings and instructions here-in before mentioned and as to the quality of workmanship or materials used on the work or as to any other question, claim, right, matter or thing whatsoever in any way arising out of or relating to the contract, designs, drawings, specifications, estimates, instructions, orders or these conditions or otherwise concerning the works or the execution or failure to execute the same whether arising during the progress of the work or after the cancellation, termination, completion or abandonment thereof shall be dealt with as mentioned hereinafter: (i)If the contractor considers any work demanded of him to be outside the requirements of the contract, or disputes any drawings, record or decision given in writing by the Engineerin-Charge on any matter in connection with or arising out of the contract or carrying out of the work, to be unacceptable, he shall promptly within 15 days request the Superintending Engineer in writing for written instruction or decision.
Thereupon, the Superintending Engineer shall give his written instructions or decision within a period of one month from the receipt of the contractor's letter.
If the Superintending Engineer fails to give his Instructions or The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above.
decision in writing within the aforesaid period or if the contractor is dissatisfied with the instructions or decision of the Superintending Engineer, the contractor may, within 15 days of the receipt of Superintending Engineer's decision, appeal to the Chief Engineer who shall afford an opportunity to the contractor to be heard, if the latter so desires, and to offer evidence in support of his appeal. The Chief Engineer shall give his decision within 30 days of receipt of contractor's appeal.
If the contractor is dissatisfied with the decision of the Chief Engineer, the contractor may within 30 days from the receipt of the Chief Engineer decision, appeal before the Dispute Redressal Committee (DRC) along with a list of disputes with amounts claimed in respect of each such dispute and giving reference to the rejection of his disputes by the Chief Engineer. The Dispute Redressal Committee (DRC) shall give his decision within a period of 90 days from the receipt of Contractor's appeal. The constitution of Dispute Redressal Committee (DRC) shall be indicated in Schedule F.
If the Dispute Redressal Committee (DRC) fails to give his decision within the aforesaid period or any party is dissatisfied with the decision of Dispute Redressal Commatee (DRC), then either party may within a period of 30 days from the receipt of the decision of Dispute Redressal Committee (DRC), give notice to the Chief Engineer for appointment of arbitrator on prescribed proforma as per Appendix XV, failing which the said decision shall be final binding and conclusive and not The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above.
referable to adjudication by the arbitrator.
It is a term of contract that each party invoking arbitration must exhaust the aforesaid mechanism of settlement of claims/disputes prior to invoking arbitration. (ii) Except where the decision has become final, binding and conclusive in terms of Sub Para (i) above, disputes or difference shall be referred for adjudication through arbitration by a sole arbitrator appointed by the Chief Engineer, CPWD, in charge of the work or if there be no Chief Engineer, the Additional Director General of the concerned region of CPWD or if there be no Additional Director General, the Special Director General or the Director General, CPWD. If the arbitrator so appointed is unable or unwilling to act or resigns his appointment or vacates his office due to any reason whatsoever, another sole arbitrator shall be appointed in the manner aforesaid. Such person shall be entitled to proceed with the reference from the stage at which it was left by his predecessor.
It is a term of this contract that the party invoking arbitration shall give a list of disputes with amounts claimed in respect of each such dispute along with the notice for appointment of arbitrator and giving reference to the rejection by the Chief Engineer of the appeal.
It is also a term of this contract that no person, other than a person appointed by such Chief Engineer CPWD or Additional Director General or Special Director General or Director The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above.
General, CPWD, as aforesaid, should act as arbitrator and it for any reason that is not possible, the matter shall not be referred to arbitration at all.
It is also a term of this contract that if the contractor does not make any demand for appointment of arbitrator in respect of any claims in writing as aforesaid within 120 days of receiving the intimation from the Engineer-in-Charge that the final bill is ready for payment, the claim of the contractor shall be deemed to have been waived and absolutely barred and the Government shall be discharged and released of all liabilities under the contract in respect of these claims. The arbitration shall be conducted in accordance with the provisions of the Arbitration and Conciliation Act, 1996 (26 of 1996) or any statutory modifications or re-enactment thereof and the rules made thereunder and for the time being in force shall apply to the arbitration proceeding under this clause.
It is also a term of this contract that the arbitrator shall adjudicate on only such disputes as are referred to him by the appointing authority and give separate award against each dispute and claim referred to him and in all cases where the total amount of the claims by any party exceeds Rs. 1,00,000/-, the arbitrator shall give reasons for the award. It is also a term of the contract that if any fees are payable to the arbitrator, these shall be paid equally by both the parties. It is also a term of the contract that the arbitrator shall be deemed to have entered on the reference on the date he issues The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above.
notice to both the parties calling them to submit their statement of claims and counter statement of claims. The venue of the arbitration shall be such place as may be fixed by the arbitrator in his sole discretion. The fees, if any, of the arbitrator shall, if required to be paid before the award is made and published, be paid half and half by each of the parties. The cost of the reference and of the award (including the fees, if any, of the arbitrator) shall be in the discretion of the arbitrator who may direct to any by whom and in what manner, such costs or any part thereof shall be paid and fix or settle the amount of costs to be so paid."
5.
Since there were disputes between the parties, after exhausting prearbitral mechanism, the petitioner invoked arbitration vide legal notice dated 25.09.2025 and thereafter, filed the present petition. 6.
Mr. Shubham, learned counsel for the respondent states that the arbitration clause is admitted.
7.
I am satisfied that there exists a valid arbitration clause and there are disputes between the parties which need to be adjudicated through the arbitral mechanism.
8.
For the said reasons, the petition is allowed and the following directions are issued:- i) The Delhi International Arbitration Centre, Delhi High Court, Sher Shah Road, New Delhi (hereinafter, referred to as the 'DIAC') shall appoint the Sole Arbitrator to adjudicate the disputes between the parties.
ii) The arbitration will be held under the aegis and rules of the The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above.
DIAC.
iii) The remuneration of the learned Arbitrator shall be in terms of DIAC (Administrative Cost and Arbitrators' Fees) Rules, 2018.
iv) The learned Arbitrator is requested to furnish a declaration in terms of Section 12 of the Act prior to entering into the reference.
v) It is made clear that all the rights and contentions of the parties, including as to the arbitrability of any of the claim, any other preliminary objection, as well as claims/counter-claims and merits of the dispute of either of the parties, are left open for adjudication by the learned arbitrator.
9.
The parties are agreeable to explore the possibility of mediation. 10.
For the said reason, list before the Delhi High Court Mediation and Conciliation Centre on 12.01.2026 at 12:30 p.m. 11.
The learned Arbitration shall enter reference after for a period of 12 weeks to enable the parties to explore the settlement. 12.
In case the settlement is not fructified, the learned Arbitrator shall enter reference.
13.
The present petition is disposed of in the aforesaid terms. JASMEET SINGH, J DECEMBER 23, 2025 / (MS) The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above.