The Project Director Adb Project Road And Bridges Department Government Of Sikkim v. Bvsr Constructions Private Limited
$~61 *
IN THE HIGH COURT OF DELHI AT NEW DELHI
+ O.M.P. (COMM) 30/2025&I.A. 12044/2025 THE PROJECT DIRECTOR ADB PROJECT ROAD AND BRIDGES DEPARTMENT GOVERNMENT OF SIKKIM .....Petitioner Through:
Mr. Sameer Abhyankar along with Mr. Rahul Kumar, Mr. Aakash Thakur, Mr.
Krishna Rastogi and Mr. Aryan Srivastava, Advs. versus BVSR CONSTRUCTIONS PRIVATE LIMITED .....Respondent Through:
Mr. S SSastry &Mr. K Venkat Satyanarayana Advs
CORAM:
HON'BLE MR. JUSTICE JASMEET SINGH
O R D E R
% 17.09.2025 I.A. /2025 (TO BE NUMBERED) 1.
The matter has been mentioned by the learned counsel for the petitioner. 2.
This is a petition seeking withdrawal of the petition on the ground that the matter has been settled.
3.
The Settlement Deed dated 15.09.2025 has been filed. 4.
In the present case, let the application be numbered under Section 151 of CPC.
5.
Mr. Sastry, learned counsel appears on behalf of the respondent and confirms that same.
6.
The application stands disposed of in the aforesaid terms. O.M.P. (COMM) 30/2025 7.
Since the matter has been settled, binding the parties to the terms of the settlement, the petition also stands disposed of. JASMEET SINGH, J SEPTEMBER 17, 2025 / (MS) The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 24/09/2025 at 12:57:33