M/S Vishwakarma Projects(India) Pvt Ltd v. National Building Construction Corporation Limited & ORS
$~18 * IN THE HIGH COURT OF DELHI AT NEW DELHI + CS(OS) 2160/2011 M/S VISHWAKARMA PROJECTS(INDIA) PVT LTD .....Plaintiff Through:
None.
versus NATIONAL BUILDING CONSTRUCTION CORPORATION LIMITED & ORS .....Defendants Through:
Mr. Ravi Krishan Chandna, Ms.
Vidushi Chandna and Mr. Udhav K Garg, Advocates for D1&2.
Mr. Daleep Dhyani, Mr. Pradeep Mishra and Ms. Lakshita Sharma, Advocates for D3.
CORAM:
HON'BLE MS. JUSTICE JYOTI SINGH
O R D E R
% 09.09.2025 1.
On 04.04.2024, adjournment was sought on behalf of Plaintiff for filing an application within two weeks for substituting the Authorized Representative (AR) of PW1. Order sheets indicate that no steps were taken thereafter by the learned counsel for the Plaintiff. In fact, on 29.10.2024, there was no appearance on behalf of Plaintiff. The same position continued on 17.01.2025, 18.03.2025 and 24.07.2025.
2.
On 24.07.2025, learned Joint Registrar noted that no application for substitution of AR of Plaintiff had been filed in terms of the order dated 13.08.2024 and no one has been appearing on behalf of Plaintiff and thus, the matter was listed before the Court for further directions. Even today, there is no presence on behalf of Plaintiff. No steps have been taken in terms CS(OS) 2160/2011 The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 11/09/2025 at 12:32:46
of the previous order for substitution of AR of Plaintiff. 3.
It appears that Plaintiff is no longer interested in prosecuting the suit. 4.
Accordingly, the same is dismissed for non-prosecution and in default.
JYOTI SINGH, J SEPTEMBER 9, 2025 Ch CS(OS) 2160/2011 The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 11/09/2025 at 12:32:46