M/S Adesh Borewell And Engineering Services v. Central Ground Water Board
$~47 *
IN THE HIGH COURT OF DELHI AT NEW DELHI
+ O.M.P.(MISC.)(COMM.) 1068/2025 M/S ADESH BOREWELL AND ENGINEERING SERVICES .....Petitioner Through:
Mr.Ajit Sharma, Adv Mr. Aditya Vikram Singh, Mr. Kanchan Kumar.
Mr.Yuvraj sing c Solanki, Ms. Parul Goyal, Advs.
versus CENTRAL GROUND WATER BOARD .....Respondent Through:
Mr. Himanshu Pathak(SPC), Mr.
Sanjay Pal(GP), MR. Chetan Sharma Adv
CORAM:
HON'BLE MR. JUSTICE JASMEET SINGH
O R D E R
% 23.12.2025 I.A. 32600/2025 Exemption allowed, subject to all just exceptions. The application is disposed of.
O.M.P.(MISC.)(COMM.) 1068/2025 1.
This is a petition filed under Section 29A (4) & (5) of the Arbitration and Conciliation Act, 1996 seeking extension of the mandate of the Arbitral Tribunal by a further period of 12 weeks for making and publishing the final Award.
2.
Mr. Sharma, learned counsel for the petitioner, states that the arguments have been concluded and judgment is reserved and hence, The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 26/12/2025 at 12:16:00
the delay.
3.
For the said reasons, issue notice.
4.
Mr. Pathak, learned counsel accepts notice on behalf of the respondent and has no objection to the petition being allowed. 5.
I am of the view that sufficient cause has been explained for the delay. 6.
In the view of the above, the petition is allowed and the mandate of the Arbitrator is extended by a period of 12 weeks from 31.12.2025. 7.
The petition is disposed of in aforesaid terms. JASMEET SINGH, J DECEMBER 23, 2025/DM The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 26/12/2025 at 12:16:00