Amit Engineers v. Chief Rolling Stock Engineer (Coach), Northern Railway
$~66 * IN THE HIGH COURT OF DELHI AT NEW DELHI + O.M.P.(MISC.)(COMM.) 34/2026 & I.A. 570/2026 AMIT ENGINEERS .....Petitioner Through:
Ms. Minakshi & Ms. Shakshi, Advs.
versus CHIEF ROLLING STOCK ENGINEER (COACH), NORTHERN RAILWAY .....Respondent Through:
Mr. Sushil Kumar Pandey, SPC with Mr. Raj Kumar, SO.
CORAM:
HON'BLE MR. JUSTICE AVNEESH JHINGAN
O R D E R
% 12.01.2026 1.
This petition is filed under Section 29A of the Arbitration & Conciliation Act, 1996 seeking extension of period for concluding the arbitration proceedings.
2.
Learned counsel for the respondent has no serious objection to the prayer made.
3.
In view of the above, the time period for conclusion of the proceedings is extended up to 31.03.2026.
4.
This petition is disposed of in the aforesaid terms. AVNEESH JHINGAN, J JANUARY 12, 2026 Ch The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 16/01/2026 at 13:09:38