Ashwani Dogra & ANR. v. Balaji Building Material Supplier Through Its Prop. Rati Ram & ANR.
$~62 *
IN THE HIGH COURT OF DELHI AT NEW DELHI
+ CRL.M.C. 500/2026 ASHWANI DOGRA & ANR.
.....Petitioners Through:
None.
versus BALAJI BUILDING MATERIAL SUPPLIER THROUGH ITS PROP. RATI RAM & ANR.
.....Respondents Through:
CORAM:
HON'BLE MR. JUSTICE ANUP JAIRAM BHAMBHANI
O R D E R
% 20.01.2026 CRL.M.A. 2009/2026 (exemption) Exemption granted, subject to just exceptions. The application stands disposed of.
CRL.M.A. 2010/2026 (condonation of delay in re-filing) By way of the present application filed under section 528 of the Bharatiya Nagarik Suraksha Sanhita 2023, the petitioners seek condonation of about 74 days' delay in re-filing the present petition. 2.
For the reasons stated in the application, which is duly supported by affidavit, the delay is condoned.
3.
The application is allowed and disposed-of.
CRL.M.C. 500/2026 4.
By way of the present petition filed under section 528 of the BNSS, the petitioners inter-alia seek quashing of summoning order dated CRL.M.C. 500/2026 The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 29/01/2026 at 13:42:14
01.06.2016 passed by the learned MM-01, South District, Saket Courts, New Delhi, in CC No.637104/2016.
5.
No one is present on behalf of the petitioners when the matter is called-out.
6.
The petition has been filed with a delay of about 10 years. 7.
At this stage, learned counsel has appeared for the petitioner via video-conferencing; and seeks leave to withdraw the petition. 8.
The petition is accordingly disposed-of as withdrawn. 9.
Pending applications, if any, also stand disposed-of. ANUP JAIRAM BHAMBHANI, J JANUARY 20, 2026/ak CRL.M.C. 500/2026 The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 29/01/2026 at 13:42:14