M/S Cantabil Retail India Ltd v. M/S Parsvnath Developers Ltd
$~8 * IN THE HIGH COURT OF DELHI AT NEW DELHI + CS(OS) 180/2017 M/S CANTABIL RETAIL INDIA LTD .....Plaintiff Through:
Mr.Aditya Saluja, Adv.
(through VC) versus M/S PARSVNATH DEVELOPERS LTD .....Defendant Through:
Mr.Manmeet Singh Nagpal, Adv.
CORAM:
HON'BLE MR. JUSTICE NAVIN CHAWLA
O R D E R
% 30.07.2024 1.
The parties have amicably settled their disputes and have executed a Settlement Agreement dated 31.05.2024 before the Delhi High Court Mediation and Conciliation Centre. 2.
The said Settlement Agreement is signed by the authorized representatives of the parties. The counsels for the parties identified their signatures on the same. They pray that the suit be decreed in terms of the said Settlement Agreement.
3.
I have perused the terms of the Settlement Agreement and find that the same to be in conformity with the laws. 4.
Accordingly, the suit is decreed in terms of the Settlement Agreement dated 31.05.2024 executed between the parties. 5.
Let a decree sheet be drawn accordingly.
NAVIN CHAWLA, J JULY 30, 2024/ns/as Click here to check corrigendum, if any The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 02/08/2024 at 11:36:26