← Library
High Court of DelhiO.M.P.(MISC.)(COMM.)/89/2018

Gwalior Bypass Project Ltd v. National Highway Authority Of India

2018-05-17Hon'Ble Mr. Justice Vibhu Bakhru2 pages

$~21 *

IN THE HIGH COURT OF DELHI AT NEW DELHI

+ O.M.P.(MISC.)(COMM.) 89/2018 GWALIOR BYPASS PROJECT LTD ..... Petitioner Through:

Mr Nilava Bandhopadhyay Mr Rahul Pandey and Mr Tushar Pandey, Advocates.

versus NATIONAL HIGHWAY AUTHORITY OF INDIA ..... Respondent Through:

Mr S. B. Upadhyay, Sr. Advocate with Mr Ramesh Kumar, Mr Samraat Singh, Mr Anisha Upadhyay and Mr Nishant Kumar, Advocates.

CORAM:

HON'BLE MR. JUSTICE VIBHU BAKHRU

O R D E R

% 17.05.2018 IA No.6892/2018 1.

Allowed, subject to all just exceptions.

O.M.P.(MISC.)(COMM.) 89/2018 2.

The petitioner has filed the present petition under Section 29A(4) of the Arbitration and Conciliation Act, 1996 (hereafter 'the Act'), inter alia, praying that the time for making the award be extended for a further period of three months from today, that is, upto 16.08.2018. 3.

The learned counsel appearing for the respondent does not object to the aforesaid request. The learned counsel appearing for the petitioner states that the Arbitral Tribunal has reserved the matter for making the final award.

4.

In view of the above consensus between the parties, the time for making the award is extended upto 16.08.2018. 5.

The petition is disposed of with the aforesaid directions. VIBHU BAKHRU, J MAY 17, 2018 MK