Pragati Construction Consultants v. Ministry Of Railways
$~24 * IN THE HIGH COURT OF DELHI AT NEW DELHI + O.M.P.(MISC.)(COMM.) 130/2018 PRAGATI CONSTRUCTION CONSULTANTS ..... Petitioner Through Ms.Richa Oberoi, Adv.
versus MINISTRY OF RAILWAYS ..... Respondent Through Mr.Jagjit Singh and Mr.Preet Singh, Advs.
CORAM:
HON'BLE MR. JUSTICE NAVIN CHAWLA
O R D E R
% 31.05.2018 IA No.7819/2018 (Exemption) Allowed, subject to all just exceptions.
O.M.P.(MISC.)(COMM.) 130/2018 This petition under Section 29A of the Arbitration and Conciliation Act, 1996 has been filed by the petitioner seeking extension of time for making of the Arbitral Award by the Sole Arbitrator adjudicating the disputes that have arisen between the parties in relation to the works for construction of two lane ROB (Road Over Bridge) in lieu of level crossing No. 69 (Spl) at KM 120/11-13 at Kamal on Delhi - Ambala Section. Learned counsel for the respondents, who appears on advance notice, submits that the respondents have no objection if the prayer is granted. Having perused the contents of the petition as also the no objection expressed by the learned counsel for the respondents, the time for making of the Arbitral Award is extended by a further period of one year with effect
from 30.06.2018.
The petition is allowed in the above terms with no order as to cost. Dasti.
NAVIN CHAWLA, J MAY 31, 2018/Arya