High Court of DelhiO.M.P.(MISC.)(COMM.)/131/2018

A2z Infra Engineering Limited v. Ntpc Electric Supply Company Ltd.

2018-05-31Hon'Ble Mr. Justice Navin Chawla1 pages

$~25 * IN THE HIGH COURT OF DELHI AT NEW DELHI + O.M.P.(MISC.)(COMM.) 131/2018 A2Z INFRA ENGINEERING LIMITED ..... Petitioner Through Mr.Abhimanyu Sharma, Adv.

versus NTPC ELECTRIC SUPPLY COMPANY LTD.

..... Respondent Through Mr.Bharat Sangal, Ms.Anindita Deka and Ms.Vidushi Garg, Advs.

CORAM:

HON'BLE MR. JUSTICE NAVIN CHAWLA

O R D E R

% 31.05.2018 This petition under Section 29A of the Arbitration and Conciliation Act, 1996 has been filed by the petitioner seeking extension of time for making of the Arbitral Award by the Sole Arbitrator adjudicating the disputes that have arisen between the parties in relation to the Contract dated 07.01.2009.

Learned counsel for the respondents, who appears on advance notice, submits that the respondent has no objection if the prayer is granted. Having perused the contents of the petition as also the no objection expressed by the learned counsel for the respondent, the time for making of the Arbitral Award is extended by a further period of six months with effect from today.

The petition is allowed in the above terms with no order as to cost. Dasti.

NAVIN CHAWLA, J MAY 31, 2018/Arya