Kurukshetra Expressway Pvt. Ltd v. National Highway Authority Of India
$~13 * IN THE HIGH COURT OF DELHI AT NEW DELHI + O.M.P.(MISC.)(COMM.) 136/2018 KURUKSHETRA EXPRESSWAY PVT. LTD ..... Petitioner Through Ms.Saman Ahsan, Adv.
versus NATIONAL HIGHWAY AUTHORITY OF INDIA .....Respondent Through Mr.Bharat Singh and Mr.Pramod Kumar, Advs.
CORAM:
HON'BLE MR. JUSTICE NAVIN CHAWLA
O R D E R
% 01.06.2018 IA No.8067/2018 (Exemption) Allowed, subject to all just exceptions.
O.M.P.(MISC.)(COMM.) 136/2018 This petition under Section 29A of the Arbitration and Conciliation Act, 1996 has been filed by the petitioner seeking extension of time for making of the Arbitral Award by the Arbitral Tribunal adjudicating the disputes between the parties in relation to the Concession Agreement dated 13.07.2010. Learned counsel for the respondent, who appears on advance notice, submits that the respondent has no objection if the prayer is granted. Having perused the contents of the petition as also the no objection expressed by the learned counsel for the respondent, the time for making of the Arbitral Award is extended by a further period of four months with effect from 07.07.2018.
The petition is allowed in the above terms, with no order as to cost. Dasti.
NAVIN CHAWLA, J JUNE 01, 2018/Arya