High Court of DelhiFAO/257/2016

M/S Emerson Process Management India Private Limited v. Fernas Construction Company Inc And ANR

2017-01-31Hon'Ble Mr. Justice Sunil Gaur1 pages

$-2, 3, 4 & 6 *

IN THE HIGH COURT OF DELHI AT NEW DELHI

+ FAO 253/2016 + FAO 254/2016 + FAO 255/2016 & C.M.No.21039/2016 + FAO 257/2016 M/S EMERSON PROCESS MANAGEMENT INDIA PRIVATE LIMITED Appellant Through: Mr. Archit Virmani, Advocate versus , FEUAS CONSTRUCTION INDIA PVT LTD AND ANR .....Respondents Through: Mr. K.C. Dubey and Mr. I3harat Saini, Advocates

CORAM:

HON'BLE MR. JUSTICE SUNIL GAUR

ORDER

% 31.01.2017 Learned counsel for appellant on instructions submits that these appeals be disposed of in terms of Settlement Agreement of 91h January, 2017 arrived at between the parties before Delhi High Court Mediation and Conciliation Centre and the said Settlement Agreement has been already acted upon.

It is ordered accordingly. The above captioned four appeals and the application are disposed of in terms of aforesaid Settlement Agreement of 9th January, 2017.

(SUNIL GAUR) JUDGE JANUARY 319 2017 S By:AMULYA