Rahee Infra Tech Limited v. Gmr Infrastructure Limited
$~42 *
IN THE HIGH COURT OF DELHI AT NEW DELHI
+ O.M.P.(I) (COMM.) 299/2016 RAHEE INFRA TECH LIMITED ..... Petitioner Through Mr.Arjun Singh Bawa, Adv.
versus GMR INFRASTRUCTURE LIMITED ..... Respondent Through Mr.P.C. Sen, Adv. with Mr.Shivanshu Singh and Mr.Udayan Verma, Advs.
CORAM:
HON'BLE MR. JUSTICE MANMOHAN SINGH
O R D E R
% 08.08.2016 Respondent is served.
Learned counsel for the respondent submits that in view of the minutes of meeting held on 4th and 5th August, 2016, the disputes between the parties have been resolved. Copy of the same is placed on record.
As per Clause 4 and 5 of the same, the petitioner is supposed to withdraw the present petition. Accordingly, the present petition is disposed of as not pressed. The interim order granted on 18th July, 2016 is vacated. MANMOHAN SINGH, J.
AUGUST 08, 2016/jk