$~O-1 * IN THE HIGH COURT OF DELHI AT NEW DELHI + CS(COMM) 872/2016 M/S JAINCO BUILDCON LIMITED ..... Plaintiff Through :

Mr.R.D.Sharma, Adv.

versus M/S DELHI JAL BOARD & ANR ..... Defendants Through :

Mr.Sumeet Pushkarna, standing counsel with Mr.Pankaj Kumar Gupta, Adv.

CORAM:

HON'BLE MR. JUSTICE YOGESH KHANNA

O R D E R

% 27.04.2018 This is a suit for recovery of 2,26,68,179.66 paise along with interest filed by the plaintiff against the defendants. During the course of proceeding, the matter was settled between the parties in the Delhi High Court Mediation Centre, New Delhi. Settlement Agreement dated 24.01.2018 was executed between the parties. Terms of the settlement are enumerated in para 7 and 9 of the Settlement Agreement. It is submitted by Ld. counsel for the parties the parties shall be bound by the terms of the settlement. The settlement has been arrived at between the parties voluntarily and without any coercion, undue influence etc.

Hence in view of the settlement so arrived at between the parties vide Settlement Agreement dated 24.01.2018 the suit stands

disposed of. The terms of settlement enumerated in para 7 and 9 shall form part of the decree. As the matter has been settled through mediation, the plaintiff shall be entitled to refund of Court Fees. Decree Sheet be drawn accordingly.

YOGESH KHANNA, J APRIL 27, 2018 VLD