Delhi Msw Solutions Ltd v. North Delhi Municipal Corporation
$~36 * IN THE HIGH COURT OF DELHI AT NEW DELHI + O.M.P.(MISC.)(COMM.) 168/2018 DELHI MSW SOLUTIONS LTD ..... Petitioner Through Mr.Rajshekhar Rao, Mr.Mutrugupta Mishra, Mr.Ambuj Dixit and Mr.Karthik Sundar, Advs.
versus NORTH DELHI MUNICIPAL CORPORATION ..... Respondent Through Mr.Sunil Goel, standing counsel with Ms.Supreet Bimbra, Mr.Mayank Goel, Advs.
CORAM:
HON'BLE MR. JUSTICE NAVIN CHAWLA
O R D E R
% 30.07.2018 IA No.9881/2018 (Exemption) Allowed, subject to all just exceptions.
O.M.P.(MISC.)(COMM.) 168/2018 & I.A. No.9880/2018 Issue notice. Mr.Sunil Goel, Advocate accepts the notice on behalf of the respondent.
This petition under Section 29A(4) and (5) of the Arbitration and Conciliation Act, 1996 has been filed by the petitioner seeking extension of time for making of the Arbitral Award by the Arbitral Tribunal adjudicating the disputes that have arisen between the parties and had been referred to the Arbitral Tribunal by order dated 02.12.2016 passed by the National Green Tribunal in Original Application No.281/2016.
Learned counsel for the respondent, who appears on advance notice, submits that without, in any manner admitting the allegations made in the petition, the respondent has no objection if the prayer is granted. As the arbitration is at the stage of the final arguments, the time for making of the Arbitral Award is extended till 31.01.2019. The petition is allowed in the above terms with no order as to cost. Dasti.
NAVIN CHAWLA, J JULY 30, 2018/Arya