Vinay Taneja v. Universal Buildwell Pvt. Ltd.
$~CP-2,3,5,6, *
IN THE HIGH COURT OF DELHI AT NEW DELHI
+ CO.PET. 669/2016 VINAY TANEJA ..... Petitioner versus UNIVERSAL BUILDWELL PVT. LTD.
..... Respondent + CO.PET. 673/2016 ANITA BERI ..... Petitioner versus UNIVERSAL BUILDWELL PVT. LTD.
..... Respondent + CO.PET. 757/2016 SANDEEP BHATIA AND SHALINI BHATIA..... Petitioner versus UNIVERSAL BUILDWELL PVT. LTD.
..... Respondent + CO.PET. 770/2016 SHAMSHER BERI ..... Petitioner versus UNIVERSAL BUILDWELL PVT. LTD...... Respondent Present: Mr.Gaurav Bahl, Adv. for the petitioner. Mr.Arjun Sawhney, Adv. with Ms.Pooja Sharma, AR, Mr.Raman Puri, Managing Director and Mr.Vikram Puri, Director for the respondent company.
CORAM:
HON'BLE MR. JUSTICE JAYANT NATH
O R D E R
% 08.03.2018 Learned counsel for the parties state that the parties have entered into a Settlement Agreement dated 20.02.2018. Pursuant to the Settlement
Agreement the first instalment of Rs.1,00,000/- each by way of demand draft has been paid to the petitioners. Learned counsel appearing for the respondent states that the respondent shall remain bound by the terms and conditions of the Settlement Agreement. Learned counsel for the petitioners has placed on record a copy of the settlement agreement dated 20.2.2018. Same is taken on record. It be sent to the Registry who may scan the same and place it on record.
Statement of the Managing Director of the respondent has been recorded separately. Respondent shall remain bound by the terms and conditions of the statement. In view of the above, present petition stands disposed of.
In case of any default liberty is granted to the petitioner to take steps as per law including for revival of the present petition. JAYANT NATH, J MARCH 08, 2018 n