Intec Capital Ltd v. Rajeshwari Infrastructure Ltd. & ORS.
$~34 *
IN THE HIGH COURT OF DELHI AT NEW DELHI
+ O.M.P.(I) 180/2015 INTEC CAPITAL LTD ..... Petitioner Through Mr.Anil Kr. Sinha, Adv.
versus RAJESHWARI INFRASTRUCTURE LTD. & ORS. ..... Respondents Through None.
CORAM:
HON'BLE MR. JUSTICE MANMOHAN SINGH
O R D E R
% 13.07.2016 Reply has not been filed despite the final opportunity granted to the respondents to the file the same.
Cost has also not been paid by the respondent. Right to file the reply is closed. Learned counsel for the petitioner states that the petitioner will take the necessary steps for the purpose of appointment of arbitral tribunal in terms of the agreement within four weeks from today. Interim order granted by order dated 23rd April, 2015 is made absolute. Liberty is granted to the respondents to move application for vacation/modification of the order, if so required. Petition is accordingly disposed of.
MANMOHAN SINGH, J.
JULY 13, 2016/vp