$~53 * IN THE HIGH COURT OF DELHI AT NEW DELHI + LPA 428/2018 GLOBAL ENERGY PVT LTD ..... Appellant Through:

Mr. Sajan Poovayya, Senior Advocate with Mr. Nishant Kumar & Mr.

Ambuj Dixit, Advocates versus THE CENTRAL ELECTRICITY REGULATORY COMMISSION & ANR ..... Respondents Through

CORAM:

HON'BLE MR. JUSTICE SANJIV KHANNA HON'BLE MR. JUSTICE CHANDER SHEKHAR

O R D E R

% 06.08.2018 CM No.31326-27/2018 Allowed, subject to all just exceptions.

Applications are disposed of.

LPA No.428/2018 & CM No.31325/2018 Learned Senior Counsel for the appellant states that there is difference between inquiry and investigation. The said submission is made with reference to the observations made by the Central Electricity Regulatory Commission in paras 52 to 54 of the order dated 9.5.2018.

It will be open to the appellant to file an appropriate application before the learned Single Judge, pointing out the aforesaid difference and accordingly make appropriate prayers.

With the aforesaid observations, the appeal is disposed of. Pending application is also disposed of.

SANJIV KHANNA, J CHANDER SHEKHAR, J AUGUST 06, 2018 tp