High Court of DelhiO.M.P.(MISC.)(COMM.)/190/2018

Quippo Oil And Gas Infrastructure Ltd. v. Shiv-Vani Singapore Pte Limited

2018-10-31Hon'Ble Mr. Justice Navin Chawla2 pages

$~27 * IN THE HIGH COURT OF DELHI AT NEW DELHI + O.M.P.(MISC.)(COMM.) 190/2018 QUIPPO OIL AND GAS INFRASTRUCTURE LTD. ..... Petitioner Through: Ms.Kartika Sharma, Mr.Abhimanyu Bhandari, Mr.Cheitanya Madan, Advs.

versus SHIV-VANI SINGAPORE PTE LIMITED ..... Respondent Through: None

CORAM:

HON'BLE MR. JUSTICE NAVIN CHAWLA

O R D E R

% 31.10.2018 1.

This petition under Section 29A of the Arbitration and Conciliation Act, 1996 (hereinafter referred to as the 'Act') has been filed by the petitioner seeking extension of time for making of the Arbitral Award by the Sole Arbitrator adjudicating the disputes that have arisen between the parties in relation to the Agreement dated 24.12.2014 executed between the parties. The respondent has been proceeded ex parte in such arbitration proceedings. 2.

Notice of the present petition has been served on the respondent through e-mail and an affidavit of service has been filed by the petitioner in this regard. None appears for the respondent in spite of such service.

3.

Having perused the contents of the petition, the time for making of the Award by the Arbitral Tribunal is extended by a further period of six months with effect from 02.06.2018.

4.

The petition is allowed in the above terms with no order as to

costs.

Dasti under the signature of the Court Master. NAVIN CHAWLA, J OCTOBER 31, 2018 RN