← Library
High Court of DelhiARB.P./280/2017

Manlift India Pvt. Ltd. v. Snehi Engineering Pvt. Ltd.& ANR.

2017-07-19Hon'Ble Mr. Justice Sanjeev Sachdeva1 pages

$~30 *

IN THE HIGH COURT OF DELHI AT NEW DELHI

+ ARB.P. 280/2017 MANLIFT INDIA PVT. LTD.

..... Petitioner Through:

Mr.

A.K.

Mishra and Mr.

Amit Kumar Pandey, Advs.

versus SNEHI ENGINEERING PVT. LTD.& ANR.

..... Respondents Through:

Ms. Ananya De, Ms. Vishakha and Mr. Anjan Sinha, Advs.

CORAM:

HON'BLE MR. JUSTICE SANJEEV SACHDEVA

O R D E R

% 19.07.2017 Learned counsel for the respondents points out that the petitioner has not issued any letter or request, requiring the respondents to refer the disputes to arbitration. Learned counsel for the petitioner seeks leave to withdraw the petition with liberty to approach after invoking the arbitration clause. The petition is accordingly dismissed as withdrawn with liberty to the petitioner as prayed for.

SANJEEV SACHDEVA, J JULY 19, 2017 'rs'