Engineering Projects (India) Ltd. v. Guru Gobind Singh Indraprastha University & ORS.
$~ * IN THE HIGH COURT OF DELHI AT NEW DELHI 88.
+ O.M.P.(I) (COMM.) 340/2016 ENGINEERING PROJECTS (INDIA) LTD.
..... Petitioner Through: Mr. J.P. Sengh, Senior Advocate with Mr. Vineet Bhagat, Ms. Aakshi Sehgal and Ms.
Manisha Mehta, Advocates.
versus GURU GOBIND SINGH INDRAPRASTHA UNIVERSITY & ORS.
..... Respondents Through: Ms. Sujata Kashyap with Mr. A.Khan, Advocates for Respondent No.2.
Ms. Anita Sahani, Advocate for Respondent No.1. Ms. Manmeet Arora and Ms. Tanuja N. Advocates for Respondent No.3.
CORAM: JUSTICE S. MURALIDHAR
O R D E R
% 03.10.2016
1. Considering that the arbitration proceedings have already commenced, the statement made by learned counsel for the Petitioner on 29th August 2016 is directed to continue till such time an order is passed by the learned Arbitrator in an application under Section 17 of the Arbitration and Conciliation Act, 1996 in accordance with law.
2. It is further clarified that this order is without prejudice to the rights and contentions of Respondent No. 3 in the arbitral proceedings between Respondent No. 3 and the Petitioner.
O.M.P.(I) (COMM.) 340/2016
3. The petition is disposed of.
S. MURALIDHAR, J OCTOBER 03, 2016 dn O.M.P.(I) (COMM.) 340/2016