$~25 * IN THE HIGH COURT OF DELHI AT NEW DELHI + O.M.P.(MISC.)(COMM.) 202/2018 TATA PROJECTS LIMITED, ..... Petitioner Through Ms. Smita Bhargawa, Ms. Sonal Gupta, Mr. Tanuj Agarwal and Ms.

Aishwarya Dash, Advs.

versus OIL AND NATURAL GAS CORPORATION LIMITED .....Respondent Through Mr. Sunil K. Jain, Mr. Punya Garg and Mr. Abhishek Jain, Advs.

CORAM:

HON'BLE MR. JUSTICE RAJIV SHAKDHER

O R D E R

% 24.08.2018 1.

This is a joint petition preferred by the parties for extension of time. 2.

I am informed that the Arbitral Tribunal entered upon reference on 31.3.2017, and, that upon expiry of statutory period of 12 months parties mutually agreed to extend the time for concluding arbitration proceedings by a period of six (6) months.

3.

I am informed that the period of six (6) months is to expire on 30.9.2018.

4.

Counsel for the parties submit that the final arguments are over and that the Arbitral Tribunal has reserved the matter for pronouncement and publication of the award.

O.M.P.(MISC.)(COMM.) 202/2018

5.

Given the aforesaid circumstances, for the moment, time is extended till 31.12.2018.

6.

The petition is disposed of in the aforementioned terms. O.M.P.(MISC.)(COMM.) 202/2018 7.

The petition is disposed of in the aforesaid terms. RAJIV SHAKDHER, J AUGUST 24, 2018 rb O.M.P.(MISC.)(COMM.) 202/2018