High Court of DelhiO.M.P.(MISC.)(COMM.)/200/2018

Galleria Property Management Services Pvt. Ltd v. Bha Associates Pvt. Ltd. & ANR.

2018-08-21Hon'Ble Mr. Justice Navin Chawla2 pages

$~23 * IN THE HIGH COURT OF DELHI AT NEW DELHI + O.M.P.(MISC.)(COMM.) 200/2018 GALLERIA PROPERTY MANAGEMENT SERVICES PVT. LTD ..... Petitioner Through: Mr.Simran Brar, Ms.Tanya Prasad, Ms.Medhavi Singh, Advs.

versus BHA ASSOCIATES PVT. LTD. & ANR.

..... Respondents Through: Mr.Kanishk Ahuja, Adv. for R-1

CORAM:

HON'BLE MR. JUSTICE NAVIN CHAWLA

O R D E R

% 21.08.2018 IA No.11107/2018 Exemption allowed, subject to all just exceptions. O.M.P.(MISC.)(COMM.) 200/2018 Issue notice. Notice is accepted by Mr.Kanishk Ahuja, Advocate on behalf of respondent no.1.

The present petition has been filed under Section 29A (4) of the Arbitration and Conciliation Act, 1996 seeking extension of time for making of the Arbitral Award by the Sole Arbitrator adjudicating the disputes that have arisen between the parties in relation to the Tripartite Maintenance Agreement dated 17th March, 2006. Having perused the contents of the petition and taking note of the fact that the arbitration proceedings are at final stage with only arguments to be addressed by the parties, time for making of the Award is extended for a further period of three months with effect

from today.

The petition is allowed in the above terms with no order as to costs.

NAVIN CHAWLA, J AUGUST 21, 2018 RN