$~ * IN THE HIGH COURT OF DELHI AT NEW DELHI + ARB.P. 658/2016 ANSAL BUILDWELL LTD ..... Petitioner Through: Mr. Manan Batra, Advocate.

versus PACIFIC CONSTRUCTION AND MANAGEMENT & ORS ..... Respondents Through: Mr. Rajat Aneja, Advocate.

CORAM: JUSTICE S.MURALIDHAR

O R D E R

% 30.01.2017

1. Mr. Rajat Aneja, learned counsel appearing for the Respondents states that without prejudice to rights and contentions of merits of the case, the Respondents have no objection to the appointment of a sole Arbitrator for adjudication of disputes between the parties. It is ordered that the arbitration by a Sole Arbitrator shall take place under the aegis of the Delhi International Arbitration Centre ('DAC').

2. The parties are directed to appear before the DAC on 22nd February, 2017 at 11am for further steps in this regard.

3. The petition is disposed of in the above terms. A copy of this order be sent to the Additional Coordinator DAC forthwith. S.MURALIDHAR, J JANUARY 30, 2017/Rm