Ajay Kumar Agrawal & ANR. v. Earth Infrastructures Limited
$~17 *
IN THE HIGH COURT OF DELHI AT NEW DELHI
+ CO.PET. 1255/2016 & CO.APPL. 5095-5096/2016 AJAY KUMAR AGRAWAL & ANR.
..... Petitioners Through:
Mr. Praveen Mittal and Mr. Kunal Kher, Advocates.
versus EARTH INFRASTRUCTURES LIMITED ..... Respondent Through:
None.
CORAM:
HON'BLE MR. JUSTICE SIDDHARTH MRIDUL
O R D E R
% 10.01.2017 In terms of the notification Regd. No.D.L.-33004/99 dated 07.12.2016, issued by the Ministry of Corporate Affairs and in particular, Clause 5 thereof, the present winding up petition under Sections 433(e), 438 & 439 of the Companies Act, 1956, stands transferred to the Principal Bench, National Company Law Tribunal, New Delhi (hereinafter referred to as the 'NCLT'). The Registry is directed to transmit the record of the present petition to the NCLT for further proceedings, in accordance with law. Counsel for the petitioner shall appear before the NCLT on 07.03.2017. SIDDHARTH MRIDUL, J JANUARY 10, 2017 mk