High Court of DelhiO.M.P.(MISC.)(COMM.)/17/2019

Rajdeep Publicity Pvt. Ltd., v. Delhi Transport Infrastructure Development Corporation Ltd. (Dtidcl) & ANR.

2019-01-16Hon'Ble Mr. Justice Navin Chawla2 pages

$~15 * IN THE HIGH COURT OF DELHI AT NEW DELHI + O.M.P.(MISC.)(COMM.) 17/2019 RAJDEEP PUBLICITY PVT. LTD.

..... Petitioner Through: Mr.Dharmender Verma, Ms.Sidiqua Fatima, Advs.

versus DELHI TRANSPORT INFRASTRUCTURE DEVELOPMENT CORPORATION LTD. (DTIDCL) & ANR.

..... Respondents Through: Mr.Amiet Andlay, Mr.A.K.Sharma, Advs.

CORAM:

HON'BLE MR. JUSTICE NAVIN CHAWLA

O R D E R

% 16.01.2019 IA 565/2019 in OMP(Misc.) (Comm.) 17/2019 Exemption allowed subject to all just exceptions. IA 566/2019 (delay) This is an application seeking condonation of 37 days delay in re-filing the petition.

For the reasons stated in the application, the delay is condoned and the application stands allowed.

OMP(Misc.) (Comm.) 17/2019 1.

This petition has been filed under Section 29A of the Arbitration and Conciliation Act, 1996 (hereinafter referred to as the 'Act') seeking extension of time for the Arbitral Tribunal to pass an Award adjudicating the disputes that have arisen between the parties. 2.

Counsel for the respondents, who appears on an advance notice, submits that the respondents have no objection if the time for making

of the Award is extended by this Court.

3.

Having perused the contents of the petition and no objection expressed by the counsel for the respondents, the time for making of the Award is extended by a further period of 12 months with effect from 16.11.2018.

4.

The petition is allowed in the above terms, with no order as to costs.

Dasti.

NAVIN CHAWLA, J JANUARY 16, 2019 RN