← Library
High Court of DelhiO.M.P.(I)/437/2015

Pondicherry Tindivanam Tollway Limited v. National Highway Authority Of India

2016-04-07Hon'Ble Mr. Justice Manmohan Singh1 pages

$~50 *

IN THE HIGH COURT OF DELHI AT NEW DELHI

+ O.M.P.(I) 437/2015 PONDICHERRY TINDIVANAM TOLLWAY LIMITED ..... Petitioner Through Ms.Priya Kumar, Adv.

with Mr.Adhish Srivastava & Ms.Tanya Tiwari, Advs.

versus NATIONAL HIGHWAY AUTHORITY OF INDIA ..... Respondent Through Mr.S.Nanda Kumar, Adv.

with Mr.Ranjeet Singh & Mr.P.Srinivasan, Advs.

CORAM:

HON'BLE MR. JUSTICE MANMOHAN SINGH

O R D E R

% 07.04.2016 Learned counsel for the parties submit that the learned Arbitrator has already entered upon reference and the arbitration proceedings are in progress.

They have no objection if the present petition be accordingly disposed of and the interim order dated 18th August, 2015 be confirmed. Ordered accordingly.

Liberty is granted to the respondent to move an application under Section 17 of the Arbitration and Conciliation Act, 1996 for modification/vacation of the said interim order before the Arbitrator, if necessary.

MANMOHAN SINGH, J.

APRIL 07, 2016/ka