Rajdeep Publicity Pvt. Ltd. v. Delhi Transport Infrastructure Development Corporation Ltd. (Dtidcl) & ANR.
$~30 * IN THE HIGH COURT OF DELHI AT NEW DELHI + O.M.P.(MISC.)(COMM.) 353/2018 RAJDEEP PUBLICITY PVT. LTD.
..... Petitioner Through: Ms.Sadiqua Fatma, Ms.M.Sidhu, Advs.
versus DELHI TRANSPORT INFRASTRUCTURE DEVELOPMENT CORPORATION LTD. (DTIDCL) & ANR.
..... Respondents Through: Mr.Amit Andley,Mr.A.K.Sharma, Advs.
CORAM:
HON'BLE MR. JUSTICE NAVIN CHAWLA
O R D E R
% 26.11.2018 IA 15933/2018 Exemption allowed subject to all just exceptions. OMP(MISC) (COMM) 353/2018 This petition has been filed under Section 29A of the Arbitration and Conciliation Act, 1996 (hereinafter referred to as the 'Act') seeking extension of time for the Arbitral Tribunal to pass an Award adjudicating the disputes that have arisen between the parties. Counsel for the respondents, who appears on an advance notice submits that the respondents have no objection if the time for making of the Award is extended by this Court.
Having perused the contents of the petition and no objection expressed by the counsel for the respondents, the time for making of the Award is extended by a further period of 12 months with effect from 16.11.2018.
The petition is allowed in the above terms, with no order as to
costs.
Dasti.
NAVIN CHAWLA, J NOVEMBER 26, 2018 RN