← Library
High Court of DelhiO.M.P. (MISC.)/25/2018

Navarag Infrastructure v. Rudra Buildwell Homes Pvt Ltd.

2018-12-10Hon'Ble Mr. Justice Navin Chawla1 pages

$~21 * IN THE HIGH COURT OF DELHI AT NEW DELHI + O.M.P. (MISC.) 25/2018 NAVARAG INFRASTRUCTURE ..... Petitioner Through: Ms.Tania Sharma, Ms.Rukmini Mukherjee, Advs. for P-1.

Mr.Akshat Gupta, Adv. for P-2.

versus RUDRA BUILDWELL HOMES PVT LTD.

..... Respondent Through: Counsel appearance not given

CORAM:

HON'BLE MR. JUSTICE NAVIN CHAWLA

O R D E R

% 10.12.2018 IA 16803/2018 Exemption allowed subject to all just exceptions. OMP(MISC.) 25/2018 This petition has been filed by the parties to the arbitration proceedings jointly, seeking extension of time for the Arbitral Tribunal to make the Award.

Having perused the contents of the petition, the time for making of the Award is extended by a further period of six months with effect from 24.10.2018.

The petition is allowed in the above terms with no order as to costs.

NAVIN CHAWLA, J DECEMBER 10, 2018 RN