$~31 * IN THE HIGH COURT OF DELHI AT NEW DELHI + O.M.P. (MISC.) 7/2017 ASHOK KUMAR ..... Decree Holder Through : Mr.Atul Parmar and Ms.Kirti Parmar, Advs.
versus EARTH INFRASTRUCTURE LTD.
..... Judgement Debtor Through : Mr.K.Sunil and Mr.Mani Shanker, Advs.
CORAM:
HON'BLE MR. JUSTICE YOGESH KHANNA
O R D E R
% 16.11.2017 This petition is under Section 29A of the Arbitration and Conciliation Act, 1996 for seeking extension of time for the arbitrator to deliver the award. Learned counsel for the respondent has no objection to the petition. Accordingly time for passing of the award by the learned arbitrator is extended till 31st December, 2017. The petition is disposed of in above terms.
YOGESH KHANNA, J NOVEMBER 16, 2017 VLD