High Court of DelhiO.M.P.(I) (COMM.)/372/2017

Pnb Housing Finance Limited v. West Coast Engineering Inc & ORS.

2017-10-16Hon'Ble Mr. Justice Jayant Nath1 pages

$~29 *

IN THE HIGH COURT OF DELHI AT NEW DELHI

+ O.M.P.(I) (COMM.) 372/2017 PNB HOUSING FINANCE LIMITED ..... Petitioner Through Mr.Ajay Uppal, Adv.

versus WEST COAST ENGINEERING INC & ORS.

..... Respondents Through Ms.Vasudha Gupta, Adv.

CORAM:

HON'BLE MR. JUSTICE JAYANT NATH

O R D E R

% 16.10.2017 The learned counsel for the petitioner says that steps for invocation/appointment of the learned arbitrator shall be taken within three weeks from today.

Subject to the petitioner taking steps within three weeks as above, the interim order passed by this court on 18.09.2017 is confirmed. The respondents are given liberty to approach the learned arbitrator if so desired for modification, vacation or variation of the interim order as per law. Petition stands disposed of.

JAYANT NATH, J.

OCTOBER 16, 2017/rk