Regen Powertech Private Limited v. Mulanur Renewable Energy Private Limited & ANR.
$~29 * IN THE HIGH COURT OF DELHI AT NEW DELHI + O.M.P.(I) 24/2017 REGEN POWERTECH PRIVATE LIMITED ..... Petitioner Through Mr.Jayant Mehta, Mr.Anshul Raajan and Mr.S.Aravindan, Advs.
versus MULANUR RENEWABLE ENERGY PRIVATE LIMITED & ANR.
..... Respondents Through Mr.Abhinav Vasisht, Sr. Adv. with Mr.Shankh Sengupta, Ms.Tine Abraham and Ms.Prerna Jain, Advs
CORAM:
HON'BLE MR. JUSTICE NAVIN CHAWLA
O R D E R
% 29.11.2017 For the reason recorded in my order passed today in OMP(I) 25/2017, Regen Powertech Pvt. Ltd. v. Green Infra Wind Solutions Ltd. & Ors., the present petition is allowed to the extent that the respondent shall give an advance notice of five working days to the petitioner before invoking the bank guarantees as mentioned in prayer (b) of the petition. The caveat given in paragraph 9 and 10 of the said order shall also apply in the present case. Petition is allowed in the above terms.
NAVIN CHAWLA, J NOVEMBER 29, 2017/vp