% 20.12.2017 IA No.15328/2017 Allowed subject to just exceptions.
The application is disposed of.
O.M.P.(MISC.)(COMM.) 63/2017 Both the learned counsels for parties have taken me through the order dated 11.11.2017 passed by the learned arbitrator which notes as follows:- "Because of the matter being kept suspended due to the possibility of exploring settlement and cancellation of dates due to difficulty of the Claimant's Counsel, the matter has been a bit delayed. Therefore, both Parties agree that they would jointly make an Application to the High Court by 15.12.2017 for extension of time for passing of the Award by 6 months, i.e. 02.08.2018."
In view of the submissions so made by both the counsels the time for conducting the arbitral proceedings stands extended for six months i.e. till 02.08.2018.
The petition stands disposed of.
Order dasti.
YOGESH KHANNA, J DECEMBER 20, 2017 M