The Singareni Collieries Companies Limited v. Boddu Swapna
HIGH COURT FOR THE STATE OF TELANGANA : HYDERABAD MAIN CASE No: W.A.No.57 of 2024 PROCEEDING SHEET S.
No.
DATE
ORDER
OFFICE NOTE 01.
25.01.2024 CJ & JAK, J I.A.No.1 of 2024 Mr. P.Sri Harsha Reddy, learned Standing Counsel for the appellant.
Mr. Vedula Venkata Ramana, learned Senior Counsel for respondent Nos.1 to 9.
Ms.
P.Bhavana Rao, learned Government Pleader for Land Acquisition for respondent Nos.10, 11 and 12.
Heard on I.A.No.1 of 2024.
For the reasons assigned in the application, duly supported by an affidavit, we find that sufficient cause on condonation of delay of 76 days in filing the appeal is made out.
In the result, delay in filing the appeal is condoned and the interlocutory application is allowed.
_____________ CJ (AAJ) _____________ JAK, J
W.A.No.57 of 2024 Writ Appeal is dismissed as withdrawn.
(Vide Separate Judgment) (B/o.) KL