THE HONOURABLE SRI JUSTICE M.S.RAMACHANDRA RAO WP.No.6211 of 2018 ORDER :

Heard the counsel for petitioner, Sri R. Vinod Reddy, counsel for respondent nos.1 to 4, and Sri Sampath Prabhakar Reddy, counsel for 5th respondent.

2.

The counsel on both sides state that the issue raised in this Writ Petition is covered by the order dt.18.12.2015 passed in WP.No.32614 of 2015.

3.

Therefore, for reasons alike, this Writ Petition is also allowed. The respondent nos.1 to 4 are directed to provide individual electricity service connection along with electricity meters to the subject property on payment of requisite charges therefor within a period of four (04) weeks from the date of receipt of copy of the order, and this shall be subject to further direction which may be issued by the State of Telangana or by the Hon'ble Supreme Court in SLP pending before it challenging the judgment of a Division Bench dt.12.09.2012 in WP.No.20407 of 2008 and batch. No order as to costs. 4.

As a sequel, miscellaneous petitions pending if any in this Writ Petition, shall stand closed.