← Library
High Court for State of TelanganaWP/7001/2018disposed of no costs

H. Yerry Swamy, v. The State Of Andhra Pradesh,

2018-03-19P Naveen Rao3 pages

THE HON'BLE SRI JUSTICE P. NAVEEN RAO WRIT PETITION No.7001 OF 2018 Dated:19.03.2018 Between:

H. Yerri Swamy, S/o. Vannurappa, Aged about 48 years, Occ: Labour, R/o. Kalaykurthi Village, Kanekal Mandal, Anantapuram District and others .. Petitioners And The State of Andhra Pradesh, rep., by its Principal Secretary, Revenue Department, Secretariat Buildings, Hyderabad and others .. Respondents The Court made the following:

THE HON'BLE SRI JUSTICE P. NAVEEN RAO WRIT PETITION No.7001 OF 2018 ORDER:

Heard learned counsel for the petitioners and learned Government Pleader for Revenue appearing for the respondents. 2.

Petitioners allege that they were granted house site pattas in the year 2013 and they are in force. However, the respondent authorities are trying to induct some new persons into the subject land and the said action is illegal.

3.

Learned Government Pleader for Revenue, on instructions, submits that the petitioners are not in occupation of the house site pattas allotted to them; the Government recently formulated a new housing scheme and since the subject land is idle and unutilized by the petitioners, the Government intends to undertake construction of houses for weaker sections and to allot the same to the beneficiaries.

4.

Admittedly, no procedure was followed while cancelling the house site pattas already granted to the petitioners. Even assuming that the statement of learned Government Pleader is true that the land allotted to the petitioners is not utilized, the competent authority has to follow due procedure before taking further steps. Thus, the action of the respondent authorities in seeking to take possession and utilize the subject land for some other purpose depriving the assignment already granted is not valid. 5.

Therefore, if the respondent authorities intend to take any action against the petitioners, they shall follow the due procedure

after putting the parties on notice and affording them due opportunity of hearing and then take further action. However, learned counsel for the petitioners fairly submits that if the petitioners are allotted constructed houses under the housing scheme according to their eligibility, they have no objection to surrender their house plots but before undertaking such exercise, they should be given due opportunity. Until the exercise in accordance with law is undertaken or petitioners are assured of allotting the constructed houses as per the housing scheme, no new person shall be inducted into the subject land. 6.

With the above observations, the Writ Petition is disposed of. There shall be no order as to costs.

Miscellaneous Petitions, if any, filed in this Writ Petition shall stand closed.

____________________ P. NAVEEN RAO, J Date:19.03.2018 KH