E. Sridhar, Jayashankar Dist And 64 Others v. Chairman And M.D., Ts Power Generation Corp. Ltd. Hyd And 4 Ot
HON'BLE SRI JUSTICE ABHINAND KUMAR SHAVILI W.P.No.16333 of 2017
ORDER
When the matter is taken up for hearing, learned counsel on either side fairly concede that the issue involved in this writ petition is squarely covered by the common order dated 24.04.2019 passed by a Division Bench of this Court in W.P.No.15741 of 2017 & batch.
Following the order dated 24.04.2019 in W.P.No.15741 of 2017, this Writ Petition is disposed of directing the petitioners to make individual representations to the Committee constituted for implementation of the scheme for absorption/regularization in terms of the guidelines issued by Telangana State Power Generation Corporation, represented by its Chairman and Managing Director vide T.G.O.O.No.98/CHM(HR)/2017 dated 01.06.2017, staking their claim along with necessary documents to demonstrate that they are working as on the cut-off date i.e., 04.12.2016 and fulfill the eligibility criteria, within a period of two weeks from the date of receipt of a copy of this order; and upon receipt of such representations, the Committee may look into the same and take a decision within a period of twelve weeks thereafter,
as per the directions of the Division Bench in W.P.No.15741 of 2017 & batch. No costs.
Pending miscellaneous petitions, if any, shall stand closed.
_____________________________________ JUSTICE ABHINAND KUMAR SHAVILI Date: 06-11-2019 rkk Note: Registry to annex copy of the order dated 24.04.2019 in W.P.No.15741 of 2017 & batch.