Enrich-Gpil(Jv) v. Union Of India
t 3405 J HIGH COURT FOR THE STATE OF TELANGANA AT HYDERABAD (Special Original Jurisdiction) THURSDAY ,THE NINTH DAY OF JANUARY TWO THOUSAND AND TWENry FIVE PRESENT THE HONOURABLE JUSTICE MOUSHUMI BHATTACHARYA WRIT PETITION NO: 11411 OF 2023 Between:
Enrich-GPIL(JV), 301, 3rd Floor, Ktvl Trade Tower, Sector-14, (atFhambi, Ghaziabad-2o'l 010, Rep. by its Authorized Representative Mr. Pradeep Kumar Mohanty ...PETITIONER AND Union of lndia, Ministry of Railways, Rep. by its Chairman, Raj Bhawan-1, Raisina Road, New Delhi-1 10001 .
Chief Electrical Engineer (Construction), South Central Railway, Secunderabad.
Chief General Manager, South Central Railway, Secunderabad. Divisional Railway Mhnager, South Central Railway, Secunderabad. RESPONDENTS Petition under Article 226 of the Constitution of lndia praying that in the circumstances stated in the affidavit filed therewith, the High Court may be pleased to issue Writ of Mandamus or any other appropriate writ or order or direction declaring the action of the 2nd Respondent in issuing the Termination Notice dt.06.03.2023 in respect of the Contract for design, supply, erection, i testing and commissioning of 25KV, 50 Hz., single phase, AC Traction Overhead Equipment with 65SQ Catenary and 1071150 Sq.
lA NO: 1 OF 2023 Petition under Section 151 CPC praying that in the circumstances stated in the affidavit filed in support of the petition, the High Cou rt may be pleased to suspend the operation of the Termination Notice dt.06.03.2C 23 lA NO: 2 OF 2023 Petition under Section 15'1 CPC praying that in the circumstances stated in the affidavit filed in support of the petition, the High Court may be pleased to direct the Respondents not take any further steps pursuant :o Termination Notice d1.06.03.2023, including awarding the balance works on tho contract for design, supply, erection, testing and commissioning of 25KV, 50 Fz., single phase, AC Traction Overhead Equipment with 6SSQ Catenary and lrlZl1 S0 Sq.
MM, HDG Copper contact wire, LT supply transformer stations, incluCing modifications to the existing OHE in view of the proposed third line between Balarshah-Manigarh, Wirur-Rechni Road, Bellampally-Mandamarri and its associated yards on Balarshah-Khazipet Section of South Central Railway to a Third party Counsel for the Petitioner: MS. K. GAYATHRI REP SRl. KATLASH NATH p S S Counsel for the Respondents: SRI GADI PRAVEEN KUMAFI (Dy. SOLICITOR GENERAL OF INDIA) The Court made the following: ORDER I !
I i i i i l I i I
THE HON'BLE JUSTTCE MOUSHUMI BHATTACHARYA WRIT PETITION NO.11411 0F 2023 Ms. K Gayathri, learned counsel representing Mr learned counsel for the petitioner.
KailashNathPSS, ORDER:
Learned counsel appearing online for the petitioner refers to a Memo filed by the petitioner for withdrawal of the writ petition.
2.
The Memo contains a letter written by the Authorized Representative of the petitioner to the concerned Lawyer stating that the parties wish to settle the dispute and the petitioner hence seeks to withdraw the writ petition.
3.
W.P.No.1 141 1 of 2023 is accordingly dismissed as withdrawn in terms of the Memo.
Interim orders, if any, shall stand vacated and all connected applications are dismissed. There shall be no order as to costs SD/.
ASSIS!^'ffFE8iL?TRH //TRUE COPY// CTION OFFICER To, I313SSISft iStS'J^U0IilR"*'oAolii'"'3%L?3HB*o'*'*'o' INDIA) [oPUC]
3. Two CD-CoPies \ \ BM BS \,(
HIGH COURT DATED:0910112025 # E STe;(..
-, 4'.i \ t,'-) l;l 0 7 Fits 2025
ORDER
\. Y., t o., =-s * PATCi iEo WP.No.11411 ot 2023 'i DISMISSING THE WRIT PETITION AS TIIITHDRAWN WITHOUT COSTS tl?r