High Court for State of TelanganaWP/16742/2019disposed of no costs

B. Mallesh Yadav v. Telangana State Southern Power Distribution Company Limited

2019-08-07A.Rajasheker Reddy3 pages

HON'BLE SRI JUSTICE A.RAJASHEKER REDDY WRIT PETITON No.16742 OF 2019 ORDER:

The grievance of the petitioner is that respondents are not receiving the application of the petitioner and not releasing the power supply to the petitioner's house at premises bearing open plot No.797 admeasuring 500 square yards in Sy.No.11/14 and 11/18 Part of Sy.No.11 situated at Khanamet Village, Serlingampally Mandal, Ranga Reddy District. Aggrieved by the same, the present writ petition is filed.

Heard learned counsel for the petitioner, Sri R.Vinod Reddy, learned Standing Counsel who takes notice for Telangana State Southern Power Distribution Company Limited, appearing for respondents 2 to 4 and Sri Sampath Prabhakar Reddy, learned Standing Counsel for respondent No.5.

It is stated by learned counsel appearing for the petitioner as well as Sri R.Vinod Reddy, learned Standing Counsel that the issue in this writ petition is covered by order of this Court dated 06-06-2019 in WP.No.10927 of 2019.

In view of the same, for the reasons alike in the said order, this writ petition is also disposed of with a direction to the respondents to receive the application of the petitioner and release the power supply to the premises of the petitioner subject to the compliance of the terms and conditions and on

furnishing an undertaking to produce the occupancy certificate from the concerned Municipal Corporation within a period of six months, and if no such occupancy certificate is produced within such period, it is open to the respondents to take appropriate action in accordance with law.

As a sequel to the disposal of this petition, miscellaneous petitions, if any, pending shall stand closed. _________________________ A.RAJASHEKER REDDY,J 07-08-2019 Nvl