M/S. Namishree Infratech v. The State Of Telangana
HON'BLE SRI JUSTICE A.RAJASHEKER REDDY WRIT PETITON No.20209 of 2019 ORDER:
Heard counsel for the petitioner, Sri R.Vinod Reddy, learned Standing Counsel for Telangana State Southern Power Distribution Corporation Limited, appearing for respondent Nos.2 and 3 and Sri Sampath Prabhakar Reddy, learned Standing Counsel for Greater Hyderabad Municipal Corporation, appearing for respondent No.4. 2.
It is stated by learned counsel appearing for the petitioner as well as Sri R.Vinod Reddy, learned Standing counsel for respondent Nos.2 and 3 that the issue in this Writ Petition is covered by the order of this Court dt.23.03.2018 in W.P.No.9789 of 2018. 3.
Therefore for reasons alike, this Writ Petition is also disposed of with a direction to the respondents to release the power supply to the premises of the petitioner subject to the compliance of the terms and conditions and on furnishing an undertaking to produce the occupancy certificate from the concerned Municipal Corporation within a period of six months, and if no such occupancy certificate is produced within such period, it is open to the respondents to take appropriate action in accordance with law.
Pending Miscellaneous petitions, if any, shall stand disposed of. There shall be no order as to costs.
_________________________ A.RAJASHEKER REDDY, J 17th September, 2019 dr