HON'BLE THE CHI EF JUSTI CE SRI THOTTATHI L B. RADHAKRI SHNAN ARBI TRATI ON APPLI CATI ON No.58 of 2018 ORDER:

Having heard the learned counsel for parties, it appears that the arbitral proceedings were not culminated within the statutory time limit in view of the fact that parties wanted to produce further documents. 2.

Taking a lenient view, the time for completion of arbitration proceedings is extended for a period of four months from today. 3.

The application is ordered accordingly.

___________________________________ THOTTATHI L B. RADHAKRI SHNAN, CJ Date: 13.07.2018 pnb/va