High Court for State of TelanganaWP/21621/2007disposed of no costs

Y. Venkata Muni Naidu, v. The A.P.S.R.T.C.,

2017-07-31M.S.K.Jaiswal3 pages

THE HON'BLE SRI JUSTI CE M.S.K.JAI SWAL WRI T PETI TI ON No.21621 of 2007 ORDER:

This writ petition is filed for issue of a writ of mandamus, declaring the action of the respondents in not paying the arrears of hire-charges for the difference kilometers of the schedule route lengths to the buses of the petitioner, bearing registration Nos.AP03V7259, AP03V7260, AP03V7261 & AP03V7262, pursuant to the joint survey conducted by the Assistant Manager, Piler Depot, dated 16.04.2005, as illegal and arbitrary and consequently direct the respondents to pay the arrears of hire charges. Heard the learned counsel appearing for the petitioner and the learned Counsel appearing for the respondents. The case of the petitioner is that pursuant to the tenders called for by the respondent Corporation, the petitioner entered into four agreements with the respondent Corporation for hiring his four buses for a period of three years, i.e.

, from 24.05.2004 to 23.05.2007, to operate in the scheduled route of Piler to Kalluru and Pileru to Kanakada, the distance of which was noted as 335 & 348 kilometers respectively. It is contended by the petitioner that as per joint survey conducted by the Assistant Manager, Pileru Depot on his request, the distance of the actual route is found more than the scheduled distances i.e., 349.08 and 371.4 kilometers, i.e., in excess of 14.8 & 23.

MSKJ,J WP.21621 of 2007 hire charges for the difference kilometers of length of routes, but the respondent Corporation did not respond.

The respondent corporation filed counter denying the contentions of the writ petitioner. It is stated that at the time of agreement the route was surveyed by the vigilance authorities and as per its report, the distance of the agreed routes were mentioned as 335 & 348 KMs. The hire charges were paid to the petitioner as per the agreements and there is no variation in the route lengths. There are no records and no proof is produced that a joint survey was conducted by the Assistant Manager, Piler Depot. Being satisfied with the vigilance survey report, and having agreed with the terms of the agreements, the petitioner entered into agreements to operate his buses on the scheduled routes, and now he is not entitled to claim any extra hire charges contrary to the agreements.

It is the main contention of the petitioner that the petitioner plied his buses more than the agreed distance of kilometers, i.e., in excess of 14.8 and 23.4 kilometers respectively every day on the scheduled routes, for which, the corporation has to pay hire charges. According to the respondents, except the vigilance report, no report is available with regard to survey of the scheduled routes.

MSKJ,J WP.21621 of 2007 conduct joint route survey of the scheduled routes, if necessary, within a period of two months there from, and consider the request of the petitioner for payment of difference of amount, if any, if the petitioner is entitled to, as per terms of the agreements entered into between the parties.

Pending miscellaneous applications, if any, shall stand closed in consequence.

__________________ M.S.K.JAI SWAL,J Date:31.07.2017 Dsr Note:

Furnish copy in one week B/o Dsr