← Library
High Court for State of TelanganaWP/8136/2012allowed no costs

Bandaru Krishna Rao v. The Govt. Of A.P.,

2016-12-01A V Sesha Sai3 pages

THE HON'BLE SRI JUSTICE A.V.SESHA SAI WRIT PETITION Nos.27186 of 2010 and 8107, 8133, 8136, 8140 and 8143 of 2012 COMMON ORDER:

Since the cause of action of the petitioners in all these cases is similar, this Court deems it appropriate to dispose of the writ petitions by way of this common order.

Heard learned counsel for the petitioners and learned Government Pleader for Panchayat Raj & Rural Development for the respondents.

In this batch of writ petitions, the petitioners challenge the action of the respondents in not adhering to the amendment issued to Clause 13 (ii) of Annexure-I of G.O.Ms.No.94 Irrigation and CAD (PW-COD) Department, dated 01.07.2003, vide G.O.Ms.No.17 Irrigation and CAD (PW-COD) Department, dated 06.02.2004, in respect of enhancement of percentage from 15 to 25 less than the estimate value of the work contract.

The petitioners are Civil Contractors. The State Government issued G.O.Ms.No.94, dated 01.07.2003. Clause 3 (ii) of Annexure-I of the said Government Order stipulated that tenders up to 15% less than the estimate may be accepted, but for tenders which are less by more than 15% of the estimate, a bank guarantee or demand draft for the difference between the tendered amount and 85% of the estimate value should be taken so that the tenderer leaves the works midway and the department is forced to call for tenders for the work once again, the bank guarantee or demand draft shall be used to finance the re-tendered work. Subsequently,

the Government of Andhra Pradesh substituted the said Clause, which reads as under:

"Tenders up to 25% less than the estimate may be accepted, but for tenders which are less by more than 25% of the estimate, a bank guarantee or demand draft for the difference between the tendered amount and 75% of the estimated contract value should be taken so that the tenderer leaves the work midway and the department is forced to call for tenders for the work once again, the bank guarantee or demand draft shall be used to finance the re-tendered work."

In the present writ petitions, the petitioners herein seek implementation of the said amended clause.

This Court while issuing notice before admission, directed the respondents not to insist on the petitioners to furnish Additional Security Deposit (ASD) contrary to Clause 13 (ii) of Annexure-I of G.O.Ms.No.94, dated 01.07.2003, as amended vide G.O.Ms.No.17, dated 06.02.2004. The said interim orders have been in existence since then.

No counter-affidavits are filed by the respondents denying the averments and allegations made in the affidavits filed in support of the writ petitions nor it is the case of the respondents that the amendment made, as stated supra, vide G.O.Ms.No.17, dated 06.02.2004, is superseded by later orders of the Government. So long as the said Clause is in existence, it is mandatory on the part of the authorities to adhere to the same.

For the aforesaid reasons, the writ petitions are allowed directing the respondents to adhere to the amended Clause 13 (ii) of

Annexure-1 as per G.O.Ms.No.17, dated 06.02.2004, if the same is in existence.

Consequently, Miscellaneous Petitions, if any pending in these writ petitions shall stand disposed of. No order as to costs. _________________ A.V.SESHA SAI, J Dt:01.12.2016.

kdl