M/S. M.Rangiah 5/0 Bramhiah Aged 80 Years v. . Divisional Engineer Assessments
HIGH COURT OF JUDICATURE AT HYDERABAD FOR THE STATE OF TELANGANA AND THE STATE OF ANDHRA PRADESH WEDNESDAY, THE TWENTY NINTH DAY OF APRIL, TWO THOUSAND AND FIFTEEN :PRESENT:
THE HON'BLE SRI JUSTICE VILAS V.AFZULPURKAR WP .NO: 13121 of 2015 Between:
M. Rangiah, S/o. Bramhiah, (SC No.511090018188) (SC No.4110900083) Gundrampally, Ramayanpet, Nalgonda District.
..... Petitioner AND 1 Divisional Engineer Assessments, Corporate office (Central Power Distribution of AP Ltd., Southern Power Distribution Company of Telangana Limited, Mint Compound, Hyderabad.
2 ADE Operation Ramannapet, Southern Power Distribution Company of Telangana Limited, Ramannapet, Nalgonda Dist. 3 Assistant Account Officer, ERO, Southern Power Distribution Company of Telangana Limited, Ramanapet, Chitiyala, Nalgonda Dist. .....Respondents Petition under Article 226 of the Constitution of India praying that in the circumstances stated in the affidavit filed herein, the High Court may be pleased to issue an appropriate writ, order or direction more particularly one in the nature of Writ of Mandamus directing the respondents action disconnecting the supply of power the petitioner who is small farmer for the demanding half of the final assessment order No.DEA/HYD/DAT 137314 D.No.10052 dated 10Feb-2015 amount of Rs.25,118/- and declaring the action of the respondent is illegal and not according to the terms and conditions of the supply where as in clause 9.3.5 it is authorized to collect only 1.5 times the normal rate levied for the petitioner.
The petition coming on for hearing, upon perusing the Petition and the affidavit filed herein and upon hearing the arguments of Sri K.V. Upendra Gupta, Advocate for the Petitioner and Sri R. Vinod Reddy, learned Standing Counsel for the Respondents, the Court made the following ORDER:
Mr. R. Vinod Reddy, learned Standing Counsel, takes notice for the respondents and seeks time to get instructions. List the matter immediately after Summer Vacation, 2015. Pending further orders, it is directed that subject to the petitioner paying half of the demanded amount within a period of 30 days from today, power supply to his service connection shall not be disconnected. ASSISTANT REGISTRAR //TRUE COPY//
For ASSISTANT REGISTRAR To 1 The Divisional Engineer Assessments, Corporate office (Central Power Distribution of AP Ltd., Southern Power Distribution Company of Telangana Limited, Mint Compound, Hyderabad.
2 ADE Operation Ramannapet, Southern Power Distribution Company of Telangana Limited, Ramannapet, Nalgonda Dist. 3 Assistant Account Officer, ERO, Southern Power Distribution Company of Telangana Limited, Ramanapet, Chitiyala, Nalgonda Dist. (Addressees 1 to 3 BY RPAD) 4 One CC to Sri K.V. Upendra Gupta, Advocate (OPUC) 5 One spare copy.
nnr HIGH COURT VVA,J DATED: 29-4-2015 NOTE: List immediately after Summer Vacation, 2015
ORDER
W.P.NO. 13121 OF 2015 DIRECTION
HIGH COURT Nnr Date of Drafting : 04-05-2015 VVA,J DATED: 29-4-2015 NOTE: List immediately after Summer Vacation, 2015
ORDER
W.P.NO. 13121 OF 2015 DIRECTION