← Library
High Court for State of TelanganaCRP/71/2015dismissed

Nalamothu Anuradha v. Goodduri Venkateswarlu

2015-01-30K.C.Bhanu4 pages

THE HON'BLE SRI JUSTICE K.C.BHANU CIVIL REVISION PETITION No.71 OF 2015 ORDER:

This Civil Revision Petition, under Article 227 of the Constitution of India, is directed against the order, dated 12.08.2014, in Civil Miscellaneous Appeal No.12 of 2012 passed by the XIII Additional District Judge, Narasaraopet, whereunder and whereby, appeal filed against the order, dated 29.02.2012, in I.A.No.1505 of 2011 in Original Suit No.416 of 2011 on the file of the Additional Senior Civil Judge, Narasaraopet, was confirmed.

2. The brief facts that are necessary for disposal of the present revision may be stated as follows:

Originally, the plaint schedule property belongs to one Bollepalli Butchaiah, who executed a registered gift deed in favour of his wife on 11.07.2005; that thereafter, donee accepted the gift deed and sold the property to the petitioner under a registered sale deed, dated 26.07.2005 for Rs.60,000/- and delivered possession to the petitioner and since then she has been in possession and enjoyment of the property; that when the respondents herein/defendants, who are strangers, having no right or title over the property are trying to interfere with the property, the petitioner herein filed a suit for permanent injunction and also filed a petition for temporary injunction.

3. Respondents herein/defendants filed counter stating that the petitioner or her predecessors-in-title have no right, title and interest over the plaint schedule property; that the plaint schedule property is part and parcel of registered sale deed, dated 10.06.1985 and therefore, they prayed to dismiss the appeal.

4. The trial Court, after considering the material on record, dismissed aforesaid Interlocutory Application and on appeal, it was confirmed.

5. Learned counsel for the petitioner herein contended that the petitioner is in possession and enjoyment of the plaint schedule property in question prior to filing of the suit; that after obtaining permission from the competent authority, the petitioner started construction in the schedule premises and therefore, he prays to admit the Civil Revision Petition.

6. Grant or refusal of interim order is guided by three well established principles viz.,

1) whether the petitioner has got prima facie right, title and interest over the property

2) whether the balance of convenience is in favour of the petitioner and 3) whether the petitioner will suffer serious irreparable injury if temporary injunction is not granted.

7. It was observed by the appellate Court in the impugned order that after obtaining ex parte ad interim injunction, the petitioner obtained permission and approval of plan from the competent authority and thereafter, started construction in the plaint schedule property. Since the property in question is a vacant site, whether the petitioner is entitled to temporary injunction pending disposal of the suit or not has to be decided in the main suit itself because the main relief and the interim relief sought for in the suit is one and the same.

8. With regard to irreparable injury, if temporary injunction is not granted, the petitioner would not suffer any irreparable injury because the property in question is a vacant site. But, under the guise of ex parte ad interim injunction, the petitioner cannot make construction in the plaint schedule property. There is no balance of convenience in favour of the petitioner. Therefore, considering all these aspects, the trial Court as well as appellate Court rightly refused to grant injunction in favour of the petitioner and that order needs no interfere by this Court.

9. Accordingly, the Civil Revision Petition is dismissed. There shall be no order as to

costs. Miscellaneous petitions, if any, pending in this revision shall stand closed. ______________________ JUSTICE K.C.BHANU JANUARY 30, 2015 YVL THE HON'BLE SRI JUSTICE K.C.BHANU

CIVIL REVISION PETITION No.71 OF 2015 DATE:30.01.2015 YVL