Gaus Amjadali Mohammed Yusuf v. The Municipal Corporation Of Greater Mumbai And ORS
507.CAA54_2018.doc Vidya Amin
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
CIVIL APPELLATE JURISDICTION CIVIL APPLICATION No. 54 OF 2018 IN APPEAL FROM ORDER (St.) No. 486 OF 2018 Gaus Amjadali Mohammed Yusuf ... Appellant/Applicant Vs.
The Municipal Corporation of Greater Mumbai & Ors.
... Respondents Mr. S.P. Srivastava, Advocate for the applicant. Mrs. Madhuri More, Advocate for the respondent/Corporation. CORAM: MRS.MRIDULA BHATKAR, J.
DATE: 29th January, 2018.
P.C.:
Upon mentioning, taken on production board.
2.
This Application is moved for condonation of delay in filing the Appeal.
3.
The learned counsel for the applicant submitted that there is a delay of 73 days in filing Appeal. The delay caused was neither intentional nor deliberate and hence, the same be condoned. 4.
In view of this submissions and the reasons mentioned in the Application, delay of 73 days is condoned.
5.
Appeal From Order be registered.
1 / 2
507.CAA54_2018.doc 6.
Civil Application is allowed and is disposed of accordingly. 7.
Place the Appeal from Order on 24th February, 2018. (MRIDULA BHATKAR, J.) 2 / 2