← Library
Bombay High CourtCAF/1935/2019delay condonatedrejected

The State Of Maharashtra (Through The Special Land Acquisition Officer No.2), Nashik And ANR. v. Shri. Ulhas Ganpat Pawar And ORS.

2022-01-24Hon'Ble Shri Justice Anil S. Kilor2 pages

Megha 63_caf_1935_2019 in fast_604_2016.doc

IN THE HIGH COURT OF JUDICATURE AT BOMBAY

CIVIL APPELLATE JURISDICTION CIVIL APPLICATION NO.1935 OF 2019 IN FIRST APPEAL (STAMP) NO.604 OF 2016 The State of Maharashtra and Anr.

...Applicants/Appellant

Versus

Ulhas Ganpat Pawar and Ors.

...Respondents

....

Mr. A.R. Patil, AGP for the Applicants-State. CORAM : ANIL S. KILOR, J.

DATED: 24th JANUARY, 2022.

P.C.:- 1.

This is an application for condonation of delay. Heard learned AGP for the Applicants-State. None for the non-Applicants though served. 2.

The learned counsel for the Applicants points out that there is delay of 236 days in filing first appeal. He has drawn attention of this Court to the reasons stated in Paragraph-2 onwards of the application and by MEGHA S PARAB Date:

2022.01.28 16:05:34 +0530 MEGHA S PARAB submits that sufficient cause has been shown by the Applicant in the application, for condonation of delay. It is submitted that the delay is not intentional but bonafide.

1/2

Megha 63_caf_1935_2019 in fast_604_2016.doc 3.

Though this application is pending from 2019 and nonApplicants are served long back, no reply has been filed to the application opposing the said application.

4.

After going through the application, more particularly, reasons stated in Paragraph-2 onwards, I am satisfied that sufficient cause has been shown in the application for condoning the delay. Accordingly, I pass the following order:

ORDER

i) The Application for condonation of delay is allowed. ii) The delay caused in filing First Appeal is condoned. The office is requested to register the First Appeal and place the same before the Court for admission. (ANIL S. KILOR, J.) Digitally signed by MEGHA S PARAB Date:

2022.01.28 16:02:35 +0530 MEGHA S PARAB 2/2